Using sjn, how do i calculate the start and finish time for each of
Using SJN, how do I calculate the start and finish time for each of the seven jobs below:
Job Arrival Time CPU Cycle
A 0 2
B 1 11
C 2 4
D 4 1
E 5 9
F 7 4
G 8 2
Thank you and please explain answer.